Whilst today there are no visible remains of a workshop maps of the time show a fairly substantially sized building between Top and Middle Locks close to the marked Saw Pit. In addition with a dry dock on site and 3 locks it seems likely that there would be a requirement for a carpenter to ply his trade and this marked building seems the most likely candidate. Indeed old records retained by the Trust show receipts in 1830/31 for stone and roofing for a Carpenter's Workshop. 

CW01 Map 1873 1888 1 cropped

It was therefore decided to rebuild the Carpenter's Workshop on the original site and to approximately the original size. The build would be a wooden structure sitting on top of a low blockwork wall and the plan would be to use it as a resource and learning centre for visitors, schools and youth groups.

CW 01a Workshop Plan

Using the old maps the exact location and size of the work shop was estimated and then plans for the construction were drawn up. Work started in the autumn of 2023 with the clearance of the site. Parts of the original brick floor were unearthed together with some large metal nails and some very rusty pieces of metal but nothing significant (unfortunately!).

The position of the walls were marked and trenches dug and concrete foundations laid allowing for the construction of the concrete blockwork.


CW02CW03

 CW04

 

 

 

 

 

 

 

 

 

CW05

 

 CW06

 CW07

 

 

 

 

 

 

 

 CW08

 CW09

 CW10

 

 

 

 

 

 

 

 

 CW11

 CW12

 CW13

 

 

 

 

 

 

 

 

 

 CW14

 CW15

 CW16

 

 

 

 

 

 

 

 

 

 

 CW17

 CW18

 CW19

 

 CW20 CW21 Erecting scaffoldingCW22 Wall Panels are delivered

 

CW23 CW24CW25

 

 

CW26CW27CW28 06 Jun 01a Looking north through CW

 

CW29 07 Jul 01cCW30 07 Jul 02 Battens on north wall ready for cladding CW31 07 Jul 03 Delivery of Cladding

 

 

CW32 08 Aug 01b Fitting the cladingCW33 08 Aug 01c First window frame in Annex fittedCW34 08 Aug 01g Lifting Ridge beam into position

 

CW35 08 Aug 04 All rafters fittedCW36 08 Aug 06 First roof tiles fitted to AnnexCW37 09 Sep 01 Insulation fitted in Annex

 

CW38 09 Sep 03 First large window frame fittedCW39 09 Sep 07a Interior view of roof trusses looking northCW40 10 Oct 02a 3 windows fitted and eaves filled

 

CW41 10 Oct 02c Main roof looking north westCW42 11 Nov 01a Fitting ridge tiles to AnnexCW43 11 Nov 03a Close up of Basil tiling main roof

CW44 11 Nov 03b Full view of CWSCW45 11 Nov 04 Scaffolding removed from north end

 

Work continues on the Carpenters Workshop.