Taking advantage of the still-dry canal at Uffington Gorse, we dug down by hand in an attempt to understand and confirm what we know about the canal structure and dimensions in our area.
We dug a number of pits and profile trenches, each time winching the spoil up out of the cutting and on to the front of the existing spoil bank. Eventually, we managed to reach the hard blue clay layer that forms the natural base of our bit of canal.
Then, using rather ad hoc measuring equipment, we were able to confirm it as being 140cm below our canal benchmark, which seems to be spot on for the anticipated depth of water once dredged.
While digging the trenches, we kept coming across loose slabs of limestone that appeared to be part of a stone retaining wall. A wall could have been built to protect the towpath in the area where boats might tie up before passing under the Uffington Arch bridge. We plan to carry out further investigations over the next few weeks to see if we can find any traces of lime cement.