Skip to content

West Vale News

Here you will see what the Branch has been doing recently and also during last year.

Older news items are available in the West Vale News Archive.

Summer 2026

At Shrivenham Canal Park –
Branch volunteers continued to improve the new permissive path from Station Road to Steppingstone Lane Bridge by spreading a thick layer of wood chippings. We were fortunate to have had the assistance with this from two teams of corporate volunteers. Branch volunteers trimmed the hedges along Steppingstone Lane to improve access. However, the length of the permissive path beyond Steppingstone Lane Bridge became somewhat overgrown with nettles and bramble, it was a lesser priority, so we decided to wait until autumn or until we had more volunteers.
Corporate volunteers also helped clear the ditch that runs along the north side of the Canal Park.
The heatwaves completely dried out the canal and the two ponds within the Park, so we took this opportunity to start dredging the canal bed by removing the layer of reed & silt. A great deal of material had to be dumped along the canal bank, for later removal.

At Uffington Gorse –
The approved Woodland Management Plan recommends increasing the diversity of the wood’s tree species and age. To achieve this, clearings (coupes) were kept free of bramble, docks etc. prior to planting a broader range of native trees later in the year. The paths were regularly maintained and cleared of broken branches etc.
In July, 20 youngsters of the 1st Stanford in the Vale Scouts & Explorers made an evening visit and spread wood chippings on 100m of the paths.
With the canal bed dry, our regular volunteers continued to remove tree stumps from the towpath and canal, an extremely large willow stump proved to be particularly difficult.

Spring 2026

At Shrivenham Canal Park –
After several years of negotiation, the Trust agreed a licence with the landowner to open a permissive public footpath along the canal from Station Road past Steppingstone Lane Bridge (SSLB) and along to Townsend Road, near the Bourton road (about a mile). The Branch originally cleared this section of towpath over a decade ago but with the withdrawal of access rights, the length beyond Steppingstone Bridge became totally blocked with bramble and blackthorn and very uneven. The 300m length from Station Road to the bridge was given priority, it was made wider, a collapsing section repaired and the path partially surfaced with wood chippings. Work started on the restoration of the path beyond the bridge, with assistance from a WRG group and then our “stump-pulling” experts from Uffington. Good progress was made before bird-nesting begun, but with limited volunteers, it remained obstructed by many tree stumps and later encroaching bramble and nettles.

At Uffington Gorse –
Following the works last autumn to clear the trees from the canal, large quantities of logs and cut branches were left around the site. The branches were collected into 3 large “brash piles”. To save further work, a tracked chipper was hired to reduce these piles to chippings that were then used to surface the muddier paths around the wood. The hedge-laying along Moor Mill Road was completed and the adjacent ditch cleared to allow light to the hedge saplings that were planted during the winter and to assist drainage. Removing the numerous logs and stumps along the towpath, proved to be an arduous task. Because the canal is in a deep cutting, the logs had to be winched up the bank, a most time-consuming operation. In a break from the hard work, our workboat was launched for an inaugural trip along the now almost clear canal.

Autumn / Winter 2025

At Shrivenham Canal Park – With the end of the dry weather, excavation of the leaking culvert that passes under the canal at the eastern end of the Park ceased and the pipes covered for the winter. The adjacent footpaths were then reinstated. Much of the spoil removed from the canal bed was moved to fill a depression adjacent to the south pond. Recent rains made the section of canal within the Park appear like a usable canal (although the water was still below design level).
A collapsing electricity pole, apparently caused quite a “firework” display, requiring SSE contractors to replace two poles. This necessitated vehicular access along the towpath in the Park. To enable this, a field gate was repositioned to replace the old pedestrian only entrance.

At Uffington Gorse – The team built steps into the slippery bank at the north end of the canal to improve public access; the materials being funded by a grant from the Trust for Oxfordshire’s Environment (TOE). Additionally, the TOE grant covered the cost of producing permanent maps and information signs at the wood’s entrances.
Laying the hedgerow on the Moor Mill Road boundary continued and 90 new saplings were planted, by corporate volunteers from the MAN Group, to supplement the hedge line.

Summer 2025

At Shrivenham Canal Park – As the ground had dried considerably due to heatwaves, we took the opportunity to investigate the leak from the canal into the culvert that goes under the canal bed at its eastern end. Excavations revealed both the original brick culvert from 1805 and the modern one installed in 1996. The brick culvert was found to be completely blocked and damaged, the more modern concrete pipe was clearly leaking at the joints. The solution will not be straightforward as to provide a full working water depth, the pipes will need to be lowered, with the brick culvert replaced by plastic pipe.
As the canal had dried out completely, visiting volunteer groups cleared the canal bed of reeds and scrub, then we begun to scrap the silt from the bed of the canal, starting near Stainswick Lane. More digging will be required to achieve a full-water depth.
Also, repairs were made to uneven towpath, towards Tuckmill Brook and towards Station Road.
On August bank holiday we had a pitch, with the Trust’s gazebo, at the ever popular Shrivenham Fete.

At Uffington Gorse –
Working from the infill area and down the towpath, as many tree trunks as possible were pulled from the canal and up onto the high bank using winches. With a steadily dropping canal water level, for several months, we continued with our aim of towpath and canal edge clearance, also removing an increasing amount of debris from the bed of the canal.
In July, two pits were excavated in the infill area that is adjacent to the road bridge. The first pit was dug into the base of the existing “bottle pit”. It yielded a large quantity of rubbish (metal, glass, pottery, masonry, plastic) and very little top soil. The silt and Kimmeridge Clay layers of the canal base were found almost 4m below the current surface and the bottom of the hole rapidly filled with water. Unfortunately, despite extending the pit to the east, there was no sign of the towpath or the expected bridge training walls. The second pit, alongside what we assume was the bridge wall, was increased by about 1m to see if any sign of a bridge arch could be located. Unfortunately, once again, nothing was found.
Later, with the canal dry, the focus changed to winching tree stumps from the bed of the canal, hard and time consuming work. About a dozen were removed, leaving almost 50m of the canal clear.
The WRG Forestry Team returned to the wood in September. With a dry canal, about 20 trees were cut up leaving the canal clear from end to end.
After recovering the logs and brash from beside the towpath work, the local team, continued to winch out the many stumps and logs still embedded in the canal.

Spring 2025

At Shrivenham Canal Park – Following the big sapling planting in December ’24, when over 300 trees were planted around the Park and along the hedge-line towards Tuckmill Brook, the new trees were mulched with wood chippings.
The far bank of the canal was cleared as far as possible. Several dead trees in the copse were felled as a safety precaution, otherwise, very wet weather hampered works, mud was the main issue, the problem was reduced by re-surfacing the paths with wood chippings and adding stone chippings to the area by the compound.
After the wet and muddy winter we had the opposite, the very dry months resulted in us spending much time watering the saplings that were planted in January and also looking after the plants, added by Shrivenham Gardening Club, in the boat “sunk” by the car park.

At Uffington Gorse – the Moor Mill hedge laying was continued in January. A partially fallen ivy-clad tree that was hung-up in another alongside the towpath caused concern and was “barriered off”. A tree surgeon was employed to fell it but it proved to be quite a complex task. It then took two work days to clear the towpath of the debris.
There was the usual flooding within the woods due to the wet weather with some paths very muddy.
Stainsbridge House care home in Malmesbury made 5 bird nesting boxes made for Coal Tits plus an owl box. A chipper was hired and created two large piles of chipping ready for the paths once the ground had dried.
Prior to starting clearance of the infill area, all the snowdrops that could be found were replanted alongside a main path where they seem to thrive. Using winches, many logs were moved off the infill area then most of the stumps before they vanished beneath nettles.


Older news items are available in the West Vale News Archive.