Rebuilding the Waiting Wall between Middle and Bottom Locks (click on photographs to enlarge)

The waiting wall which lies between Bottom and Middle Lock at Pewsham had, it appears, been originally built with large stones with a clay infill behind to ensure it was water-tight.

Pewsham Waiting Wall 1

Over the years since the canal was abandoned the wall had badly weathered, collapsed in places and a number of large trees had taken root in the wall itself further destabilising it.

 

 

 

Pewsham Waiting Wall 4

 

 

 

Our first task was to make the site accessible and then to remove four trees that were on the line of the wall. Note that other trees will be planted elsewhere to replace these. Once this was done the remains of the original wall was removed.

 

 

Pewsham Waiting Wall 5

Once the site was totally clear work on the new wall began.

 

Pewsham Waiting Wall 7

 

 

 

 

 

 

 

Pewsham Waiting Wall 8

 

 

This was to be constructed of concrete blocks below the water line, bricks above the water line and then topped with concrete coping.

 

Pewsham Waiting Wall 9

 

 

 

 

 

 

Pewsham Waiting Wall 10

 

 

 

Pewsham Waiting Wall 14

 

 

 

 

 

 

 

 

 

After several months and a lot of hard work by our volunteers the main part of the waiting wall is complete.

Pewsham Waiting Wall 15

 

 

 

Pewsham Waiting Wall 16

 

 

 

 

 

Pewsham Waiting Wall 18

 

 

 

 

It connects to the wing wall of Bottom Lock, which had earlier been rebuilt and will, in time, connect to the wing wall of Middle Lock when that is rebuilt.

 

 

 

In addition it was advised by the Trust engineer that a Spill Weir  should be incorporated into the waiting wall to ensure that any excess water would not over-top the lock gates but would instead go through the spill weir and drain past Bottom Lock and back into the canal.

Back to MCC Projects Main Page

Back to MCC Home Page

 

Rebuilding the Waiting Wall between Top and Middle Locks (click on photographs to enlarge)

This was built in two phases, the first in 2016 and the second in 2022/23.

Phase 1:   There was very little left of the waiting wall between Top and Middle Lock. There was a brick wall close to Middle Lock which as probably part of the lock wing wall but little else. It seems likely that the actual waiting wall had been constructed much as the one between Middle and Bottom Lock i.e. as a roughly built stone wall with a clay infill behind and over the years most of this had disappeared. Even the foundations were almost non-existent. We had to therefore  build the new wall from scratch,

 WW01

WW02

  The wall was to be build just to the left of the canal line as shown in the picture on the left. A pipe was laid to carry the canal water and then this area was filled in so construction could begin. After the foundations were laid concrete blocks were laid below the water line.

 

 

 

 

 

 

 

 WW03

 WW04

 Once the wall got to a cerain height a brick facing was laid and then a concrete coping was added to the top. Begind the wall a brick retaining wall and steps were added. The first phase was complete! 

 

 

 

 

Phase 2: 

 WW05


WW06

 

  Vegetation was cleared and  bricks for the original wall were removed ready for cleaning and re-use elsewhere. The line of the wall was then excavated. 

 

 

 

 WW07

 Once cleared the area was ready for the concrete foundations to be poured.

 

WW08

 

 

 WW09

WW10

 

 The concrete blocks could then be laid and despite the wet autumn weather good progress was made.

 

 

 

 

 

 

 

 WW11

 WW12

 

A concrete backill was laid and work continued on building up the wall, making sure it was level as we went.

 

 

 

 

 

 

 

 WW13

WW14

 

 Once we reached just below the water line a brick facing was laid. As we got higher scaffolding was erected to ensure safe working for our volunteers

 

 

 

 

 

 

WW15

 

WW16

 

 Once the top of the blocks was reached the back of the wall was back-filled with clay and earth. Shuttering was then constructed ready for constructing the concrete coping which was laid in 1 metre sections.

 

 

 

 

 

 

WW17

 

WW18

 

 All hands on deck to lay the coping! 

 

 

 

 

 

 

 

 WW19

 

 WW20

 Once completed the scaffolding was removed and  a layer of top soil was added behind the wall, with grass seeding.

 

 

 

 

 

 

 

WW21

 

WW22

 A view of the cmpleted wall looking north towards Top Lock. The southern end of the wall will eventually be joined to the wing wall of Middle Lock when it is constructed. Another view of the wall looking south

 

 

 

 

 

 

 

WW23

 

WW24

 

 Before and After photographs

 

 

 

 

 

 

Back to MCC Projects Main Page

Back to MCC Home Page